Schedule
- Groundbreaking - November 5, 2012
- Project Kick-off - November 7, 2012
- Side Street Parking striping - November 2012
- Construction Start - January 2013
- All major construction activities were complete by November 27, 2013.
- No construction will occur between November 28, 2013, and January 1, 2014. Minor final activities (planting revisions, installation of sidewalk art and amenities, concrete/warranty work, striping etc.) will occur after the New Year.
Funding
The Pacific Avenue Streetscape project is funded primarily by Federal and State grants with City matching funds.
US Environmental Protection Agency grant
|
$1,500,000
|
US Federal Highway Administration grant
|
$2,578,163
|
Washington State 2012 Jobs New Act Grant
|
$3,000,000
|
City Funding
|
$3,496,359 |
Design
The project design includes all grant-required elements and amenities, and has been vetted through the Landmarks Commission and reviewed by WSDOT.
Additional Information
South 15th to South 17th Streets, West Side
South 11th to South 15th Streets, East and West Sides