This project will fill in missing sidewalk sections on the west side of N Vassault Avenue and will install or upgrade ramps and driveways to meet current ADA standards.  The project will also include the replacement of the retaining wall located at the south end of the project for about four hundred and fifty feet along the west side of the road.  In the wall section of the project the rarely used on-street parking will be removed to accommodate the retaining wall and new sidewalk.

 

The City recently awarded a contract to Global Contractors, LLC for the construction of missing sidewalk sections along the west side of North Vassault Street and construction of a retaining wall near the southern end of the project.

Public Meetings

An Open House was held at the Point Defiance Elementary School on March 2, 2015, from 5:30 PM to 6:30 PM.  

Project Funding

Source Amount 
City Funds $345,000
TIB Urban Sidewalk Program Grant $398,121
Total $743,121

Budget

Item Amount
Design $154,000
Construction Engineering $113,793
Construction $477,355
Total $745,148

Schedule

Task Estimated Start Date Estimated End Date
Design January 2, 2014 September 30, 2014
Right-of-Way October 1, 2014 January 31, 2015
Advertise February 1, 2015 March 31, 2015
Construction July 27, 2015  September 30, 2015

Questions and Comments