Orchard Street–Lakewood Drive Improvements

How to Translate this Web Page

This Web Page is Available in 100+ Languages

Need this web page translated? Please use the ‘Language’ button in the ribbon at the top of this web page to translate this page into one or more of 100 languages available.  ¿Necesita traducir esta página web? Utilice el botón "Idioma" en la cinta de opciones en la parte superior de esta página web para traducir esta página a uno o más de los 100 idiomas disponibles.   ត្រូវការ web page នេះ translated? សូម ប្រើ ប៊ូតុង 'ភាសា' នៅ ក្នុង ribbon នៅ ផ្នែក ខាង លើ នៃ ទំព័រ បណ្ដាញ នេះ ដើម្បី បកប្រែ ទំព័រ នេះ ទៅ ជា មួយ ច្រើន នៃ 100 ភាសា ដែល មាន ។  Нужна ли эта веб-страница переведена? Пожалуйста, используйте кнопку «Язык» на ленте в верхней части этой веб-страницы, чтобы перевести эту страницу на один или несколько из 100 доступных языков.  Cn trang web này được dch? Vui lòng s dng nút 'Ngôn ng' trong ruy-băng đầu trang web này để dch trang này thành mt hoc nhiu hơn 100 ngôn ng có sn.  페이지를 번역해야 합니까? 페이지 상단의 리본에 있는 '언어' 버튼을 사용하여 페이지를 사용할 있는 100 이상의 언어로 변환하십시오.

This Web Page is Available in 100+ Languages

Need this web page translated? 需要翻译此页面吗? ត្រូវការបកប្រែភាសាគេហទំព័រនេះមែនទេ? 웹페이지의 번역이 필요하십니까? Хотите перевести эту страницу? ¿Necesita traducir esta página web? Kailangan isalin ang pahina sa web na ito? Bạn cần dịch trang web này?

 

Project Description

This partnership project includes roadway and pedestrian improvements to the Orchard Street/Lakewood Drive, a major arterial providing vital motility to Tacoma, University Place and Lakewood, between South 56th Street and South 74th Street.

 

There is an intent for a phased approach for the remainder of design and identification of right-of-way needs for this project. The partner agencies plan on submitting a future joint grant application(s) for federal or state funding for phased improvements to this corridor. A portion of the project is currently owned by Pierce County and planned for annexation by Tacoma. Additional information about the planned annexation is available at www.cityoftacoma.org/Manitou.

 

 site map

 

Project Schedule

This project is currently only funded for the conceptual design phase. An estimated construction start date has not been set yet and will be dependent on future funding.

 

Project Funding

This project is currently only funded for the conceptual design phase. The table below summarizes the current funding sources for the project.

 
Source Amount
City of Tacoma Streets Initiative Fund 1085          

$61,728.69

City of University Place $10,339.43
City of Lakewood $8,498.88
Total 30% Design Cost $80,567

 

Public Outreach

A virtual public meeting was held with staff from the City of Tacoma, City of University Place, and City of Lakewood (Partner Agencies) on December 15, 2022. A video recording of the presentation and a Questions and Answers (Q&A) summary are provided below.

Additional Information

When preliminary (30%) plans are complete, a link to those plans will be made available on this website.

 

For additional project information, please contact Charla Kinlow, Project Manager, at (253) 208-4223 or ckinlow@cityoftacoma.org.