This project will fill in missing sidewalk sections on the west side of N Vassault Avenue and will install or upgrade ramps and driveways to meet current ADA standards. The project will also include the replacement of the retaining wall located at the south end of the project for about four hundred and fifty feet along the west side of the road. In the wall section of the project the rarely used on-street parking will be removed to accommodate the retaining wall and new sidewalk.
The City recently awarded a contract to Global Contractors, LLC for the construction of missing sidewalk sections along the west side of North Vassault Street and construction of a retaining wall near the southern end of the project.
Public Meetings
An Open House was held at the Point Defiance Elementary School on March 2, 2015, from 5:30 PM to 6:30 PM.
Project Funding
City Funds |
$345,000 |
TIB Urban Sidewalk Program Grant |
$398,121 |
Total |
$743,121 |
Budget
Design |
$154,000 |
Construction Engineering |
$113,793 |
Construction |
$477,355 |
Total |
$745,148 |
Schedule
Design |
January 2, 2014 |
September 30, 2014 |
Right-of-Way |
October 1, 2014 |
January 31, 2015 |
Advertise |
February 1, 2015 |
March 31, 2015 |
Construction |
July 27, 2015 |
September 30, 2015 |
Questions and Comments
The City of Tacoma is managing the project. Contact City Project Manager Darius Thompson with questions or concerns at (253) 573-2410 or via email.