Shoreline: PSE has permission through a Shoreline Substantial Development Permit (SSDP) to request development permits for one loading arm and loading platform at the TOTE site. This includes a cryogenic pipe from their liquefaction facility, a fueling arm, and the required water-side facility for the fueling arm (including containment). The current shoreline permit on the Hylebos waterway, as reduced from what was originally proposed, is limited to stormwater outfall repair and improvements as well as demolition of the deck on the existing pier, shoreline vegetation, some grading/graveling, and security fencing.
According to PSE and TOTE, the configuration of the fueling arm is unique to the TOTE ships, and a conventional bunker barge could not be fueled using this infrastructure. Further, the TOTE site does not have moorage facilities or shoreline permit approval for construction to accommodate a bunker barge.
The City has specifically asked PSE to discuss what further permitting would be needed to accommodate bunker barging at the site. Without knowing what kind of vessels would propose to use the site, the permitting path cannot be determined.
However, it is recognized by all parties that additional shoreline permitting and public review, as well as additional review by the Coast Guard (which has authority over vessels) would be required.
The Shoreline Hearings Board (SHB) upheld the City’s permitting decision following a week-long hearing in May of 2016. This SHB decision was appealed by the Puyallup Tribe on August 16, 2016. The next hearing for the Shoreline Permit will be set sometime in 2017. Under state law, unless the petitioner obtains a stay while the appeal is pending, the permit applicant is entitled to rely on the last decision — in this case the decision of the SHB upholding the City’s decision. (A “stay” means to stop something temporarily through a court order.) What that means is that, even though there is an additional appeal pending, PSE can proceed with its project under the SSDP, but would do so at the risk of later reversal in the pending appeal. At this time, there is no stay in place, nor is there any request for a stay pending decision by the court.
Upland – PSE Site: This is the site on the east side of Alexander, neighboring the Hylebos Waterway. The EIS analyzed the environmental impacts of the liquefaction facility. This includes an LNG storage tank, the liquefaction facility (refrigerants propane, isopentane, and ethylene), the cryogenic pipeline and loading facility for TOTE, and two truck loading bays on the west side of the facility. Up to two tanker trucks per day would arrive empty at the Tacoma LNG Facility and leave carrying LNG to market, generally to a local user. (The EIS also analyzed a bunkering facility in the Hylebos, which has since been removed from the proposal.)
Other Activities: The proposal also includes extension of the existing natural gas distribution infrastructure with a new limit station and gate station in Pierce County, and approximately five miles of new pipeline (12"-16" diameter) in two segments (Pierce County, Fife, and Tacoma).
Current permitting: The following table shows the current status of development permits at the site. PSE has begun demolition of structures, utility and ground improvements, and tenant improvements to one building at the site. PSE has yet to apply for permits for the development of the LNG facility. These permits are expected to consist of one or more foundation and trenching permits as well as the building permit for the tank itself. All permits may be viewed on our permits portal by entering the permit number in the search field.