• City of Tacoma QA
  • City of Tacoma OpenData




 

North Vassault Project Update - September 9

North Vassault Project Update - September 9

On North Vassault Street between N 46th Street and N 48th Street, the contractor is continuing work on the rock wall.  One lane will remain opened at all times with flaggers in place while  work is underway.  Both lanes are temporarily reopened at this time.

 

The contractor will continue to remove and replace curb and gutters, sidewalks, ramps, and driveway approaches throughout the project.

 

Vehicle and pedestrian detour routes will remain in place for the duration of the project.

 

Project completion is expected to be the end of September 2015.



]]>