South Tacoma Way Update - December 11

South Tacoma Way Update - December 11

S. 56th to S. 58th Street - East side

Sidewalks and driveways are scheduled to be poured and cured by December 14, 2015.

 

S. 56th to S. 58th Street - West Side

The demolition, grading of the sidewalk, forming of ADA ramps and driveways will begin December 3, 2015; Concrete will be poured on December 14, 2015 and work is expected to be completed by December 23, 2015.

 

S. 58th to S. 66th Street West Side

Completed

 

S. 58th to S. 66th Street East Side

Demo will begin December 9, 2015 and concrete is scheduled to be poured and cured by December 18, 2015.

 