South Tacoma Way Update - Feb. 10

South Tacoma Way Update - Feb. 10

REVISED DATES FOR OVERLAY WORK

 

Overlay work on the west side of South Tacoma Way from S. 55th to S. 66th street has been delayed  due to weather conditions. The revised dates are Feb. 17 & 18, weather permitting.  Work will begin at 8:15 pm and end at 5:00 am.

 

While work is underway, no traffic will be allowed over the newly placed asphalt along South Tacoma Way. Drivers are asked to park along the secondary arterial streets.

  

In addition, traffic will be routed to these arterial streets: S. Washington Street and S. Puget Sound Avenue. Detour and road closed signs will be in place, and local access and protected walkways will be maintained at all times.

  

The current project is scheduled to be completed by the end of February 2016. We appreciate your patience during construction.



]]>