Union Ave will continue to be one lane in each direction. The contractor is continuing to prepare the west half of bridge deck for the concrete overlay that will take place August 11 to 14. The week of August 17 the contractor will be removing and replacing the expansion joints on the west half of the bridge and installing the ADA ramps. Upon completion of these tasks the traffic will be rerouted to the west half of the bridge so the contractor can begin hydro milling the east half.