Project Description
The project will complete a pavement maintenance grind and overlay for one block in each direction from the intersection of South I Street and 6th Avenue. Traffic and bicycle lanes will be re-striped.
Map

Project Schedule
Planning Completed |
December 2021 |
Design Completed |
July 2022 |
Construction Planned |
March 2023 - July 2023 |
Project Funding
Puget Sound Regional Council – Urban Arterial Program Grant |
$ 765,315 |
City Streets Initiative (1085 Fund) |
$ 326,326 |
Total |
$1,091,641 |
Contact Information
The City of Tacoma Project Manager is Jon Kulju, PMP, (253) 591-5204 or jkulju@cityoftacoma.org.