Need this web page translated? Please use the ‘Language’ button above to translate this page into one or more of 100 languages available. 需要翻译此页面吗?请使用上方的“语言”按钮,将此页面翻译成一种或多种语言,总计支持100种语言翻译。 ត្រូវការបកប្រែភាសាគេហទំព័រនេះមែនទេ? សូមប្រើប៊ូតុង 'ភាសា' ខាងលើដើម្បីបកប្រែភាសាទំព័រនេះជាភាសាមួយ ឬច្រើនជាង 100 ភាសាដែលអាចប្រើបាន។  이 웹페이지의 번역이 필요하십니까? 위의 ‘Language’ 버튼을 이용해 100여 개 언어 중 하나로 이 페이지를 번역할 수 있습니다.   Хотите перевести эту страницу? Воспользуйтесь кнопкой "Язык" выше, чтобы перевести эту страницу на один или несколько из 100 предложенных языков   ¿Necesita traducir esta página web? Utilice el botón “Idioma” de arriba para traducir esta página a uno o más de los 100 idiomas disponibles.   Kailangan isalin ang pahina sa web na ito? Mangyaring gamitin ang pindutan na ‘Wika’ sa itaas upang isalin ang pahinang ito sa isa o higit sa 100 wika na magagamit.   Bạn cần dịch trang web này? Vui lòng sử dụng nút ‘Ngôn ngữ’ ở trên để dịch trang này sang một hoặc nhiều thứ tiếng trong số 100 ngôn ngữ sẵn có

 

 

Project Description

 

The Links to Opportunity Streetscape Project (LTO) completes the construction of the sidewalk and streetscape upgrades in the Stadium and Hilltop Districts along the Hilltop Tacoma Link Extension Project. The scope of the improvements will include bringing existing sidewalks to ADA compliance, adding streetscape features including varying concrete sidewalk colors and paver designs, sandblasted banding, poetic inscriptions in granite panels, bronze historic plaques, upgraded pedestrian lighting, street furniture, bicycle racks, corrals and repair station, street trees, and landscaping.

 

Project Concepts

 

Proj Concepts

 

Details (Bench)

 

Project Map

 

Proj Map

 

The LTO Project begins at the intersection of N 1st Street and Tacoma Avenue, continues west to Division Ave, following the Hilltop Tacoma Link Extension project to Martin Luther King Jr. Way south to S 19th Street.

 

Project Construction and Equity in Contracting

Public Works Department has engaged with Community and Economic Development Department to fully embrace the Equity in Contracting Program to reach out to MWBE contractors and communicate the opportunities to bid and subcontract for these projects.


The overall construction project has been divided into five separate areas, breaking up the corridor into managed construction packages ranging from $650K to $3.2M (See map above).


The City conducted outreach events where Prime Contractors and Subcontractors were invited to learn about the upcoming opportunities on the LTO packages, City of Tacoma's Equity in Contracting Program requirements, the Minority Business Development Agency (MBDA) office and network with potential partners. More information about the event is available here: MBDA Opportunities Site

For more information on the City’s Equity in Contracting Program visit the Equity in Contracting Website

 

 Links to Opportunity Streetscape EIC Requirements: Project Estimated Construction Cost

Package 1 MBE TBD WBE TBD SBE TBD                                Estimated $800,000
Package 2 MBE TBD WBE TBD SBE TBD                 Estimated $650,000
Package 3 MBE 10% WBE 8% SBE 14%   Estimated $3,200,000
Package 4 MBE TBD WBE TBD SBE TBD
Estimated $1,000,000
Package 5 MBE TBD WBE TBD SBE TBD
Estimated $1,350,000

 

Public Wi-Fi

Infrastructure for Public Wi-Fi is also being incorporated into the project as part of the City of Tacoma Digital Equity Program.  Wi-Fi equipment will be installed at a later time. (Click the link to read more about the program.) 

 

  

WiFi Map

 

Streetscape Concept

 

concept map

Streetscape concept for street furniture, street trees and decorative concrete

 

Project Schedule Updates

 

Phase

Date

Planning

December 2018

Design Completed

August 2019

Right of Way Completion

Fall 2022

Construction Begin

Spring 2023 (pending Sound Transit Schedule)

Duration

Estimated 18 months

 

Project Funding Update

 

Funding for the LTO project has been secured through several sources including Street Initiative funds, Community Development Block Grant, Sound Transit System Access Fund Grant and the City Real Estate Excise Tax. Additional funding was requested from the WA State Capital Budget. Construction cost estimated at $12 Million dollars for the construction and administration of the project. 

 

Source

Amount

Streets Initiative Fund

$   820,000

Community Development Block Grant

$2,000,000

Sound Transit System Access Fund Grant

$3,500,000

City Real Estate Excise Tax

$4,000,000

Washington State 2021-2023 Capital Budget

$2,000,000

 


Project Construction Contacts 

Construction of the project will impact access to residences and business for limited periods of time to install the new sidewalks. The Public Works and Community & Economic Development are working closely with the community to ease the disruption and promote communication through direct access to staff, postcard mailers and other media. The construction team will strive to keep the community informed of the construction schedule and be responsive to issues that may arise. More information will be shared as construction nears. In the meantime, please reach out to contact someone on the team at the following: 
 

Project Contact Information

 

City of Tacoma Project Manager: Jon Kulju, PMP, (253) 591-5204 or jkulju@cityoftacoma.org.

 

Carol Wolfe, cwolfe@cityoftacoma.org 253.591.5384 - City of Tacoma, Community and Economic Development Division Manager 

Selena Choy, selena.choy@hac-tacoma.org (253) 301-3299 Hilltop Action Coalition, Program Manager