Progress Update-15th Street Bridge
Work on the bridge is complete.
Construction Update
The project is currently 95% complete and will wrap up fall 2017. At this time the project is awaiting delivery of the remainder of the plantings, the final set of pavers and some signage. Once these materials have been delivered final installation and punch list items will be completed.
Overview
This project will complete an important link in Tacoma’s non-motorized system, connecting the waterfront to downtown with multiple city and regional trails. Traversing the steep hills of Tacoma is a challenge – the gentle grade of this former rail corridor provides an easier walking and cycling alternative. Construction of this multi-use path includes wayfinding, lighting, stormwater improvements, landscaping, public art, and amenities. The first phase of the project is located along the former BNSF rail line running between South 15th Street and Dock Street.
Outreach and Public Involvement
Public Meetings
Project Funding Update
FHWA STPE Grant |
$465,000 |
City Funds |
$1,820,000 |
State Dept. of Ecology Grant |
$53,330 |
Metro Parks |
$360,000 |
Puget Sound Regional Council Grant |
$1,919,372 |
Total |
$4,617,702 |
Budget Phase 1
Conceptual Design |
$352,000 |
Design |
$660,557 |
Construction Engineering |
$402,357 |
Construction |
$3,202,788 |
Total |
$4,617,702 |
Schedule
Design |
May 2014 |
December 2014
|
Re-Advertise/Award |
June 2016 |
August 2016
|
Construction |
Sept 2016 |
October 2017
|
Questions and Comments
The City of Tacoma is managing the project. Contact City Project Manager Chris Storey with questions at (253) 573-2484 or via email.