Sheridan Avenue Missing Links Sidewalks

This Web Page is Available in 100+ Languages

Need this web page translated? 需要翻译此页面吗? ត្រូវការបកប្រែភាសាគេហទំព័រនេះមែនទេ? 이 웹페이지의 번역이 필요하십니까? Хотите перевести эту страницу? ¿Necesita traducir esta página web? Kailangan isalin ang pahina sa web na ito? Bạn cần dịch trang web này?

 

How to Translate this Web Page

This Web Page is Available in 100+ Languages

Need this web page translated? Please use the ‘Language’ button above to translate this page into one or more of 100 languages available. 需要翻译此页面吗?请使用上方的“语言”按钮,将此页面翻译成一种或多种语言,总计支持100种语言翻译。 ត្រូវការបកប្រែភាសាគេហទំព័រនេះមែនទេ? សូមប្រើប៊ូតុង 'ភាសា' ខាងលើដើម្បីបកប្រែភាសាទំព័រនេះជាភាសាមួយ ឬច្រើនជាង 100 ភាសាដែលអាចប្រើបាន។  이 웹페이지의 번역이 필요하십니까? 위의 ‘Language’ 버튼을 이용해 100여 개 언어 중 하나로 이 페이지를 번역할 수 있습니다.   Хотите перевести эту страницу? Воспользуйтесь кнопкой "Язык" выше, чтобы перевести эту страницу на один или несколько из 100 предложенных языков   ¿Necesita traducir esta página web? Utilice el botón “Idioma” de arriba para traducir esta página a uno o más de los 100 idiomas disponibles.   Kailangan isalin ang pahina sa web na ito? Mangyaring gamitin ang pindutan na ‘Wika’ sa itaas upang isalin ang pahinang ito sa isa o higit sa 100 wika na magagamit.   Bạn cần dịch trang web này? Vui lòng sử dụng nút ‘Ngôn ngữ’ ở trên để dịch trang này sang một hoặc nhiều thứ tiếng trong số 100 ngôn ngữ sẵn có

 

 

Project Description

Construct sections of sidewalk along Sheridan Avenue between South 72nd Street & South 84th Street to provide sidewalks on at least one side of the street along the entire length. Project includes constructing sidewalks, ADA compliant crossings, sections of curb with areas of landscape/trees, and improving bus stops.

 

Project Benefits

The project will provide safer connections between major arterial streets, a safer walking route to Birney Elementary, improved Pierce Transit Route 48 bus stops, and amenities.

 

Parking Impacts

Residential parking will be impacted in some areas and restricted per Chapter 9.17 of the Tacoma Municipal Code which does not allow parking on the sidewalk or planting strip.

 

Project Updates

January 21, 2021: Project construction contract has been awarded and contractor should commence work early in February. Construction should last 10 to 12 weeks dependent upon weather and unforeseen conditions.

 

Project Schedule

Phase

Date

Planning Completed

May 2019

Design

June - September 2020

Right of Way

N/A

Construction

Winter 2020/2021

 

Project Funding Update

Working with the community and responding to the need, City Council Member Chris Beale requested funding for this project during the 2019/2020 budget planning cycle.

 

Source

Amount

City of Tacoma REET

$600,000

1085 Streets Initiative Fund

$ 79,395

  

Vicinity Map

Project Manager is Jon Kulju. He can be contacted by phone at (253) 591-5204 or email at JKulju@cityoftacoma.org.

 



]]>